Cleanroom Partitions For Medical Technology Provider, Devon

Haldons Construction

Background 

After successfully working with Haldons Construction Consultants at a medical technology company in 2017, Stancold were asked to complete a second cleanroom partitioning project on the same site.

Process

As this was a complex project and was to be conducted in a live environment, the Stancold team attended numerous site visits with Haldons and the end client to discuss finer details of the installation process. Working closely with both parties provided the necessary support in the pre-construction stage of the project.

Solution

As per the client’s requirements, Stancold dismantled and removed the temporary walls in place and then erected 500m² of new cleanroom partitions using Kingspan Quadcore 80mm panels integrating a hinged personnel access door.

Using our strong expertise of working in a live environment, appropriate measures were implemented to ensure no construction debris left the area outside of the temporary screens and panels were cut away from the construction area, allowing the client’s working operations to continue as normal.

Contact Mark Kendrick for cleanroom and laboratory enquiries

Communication from Stancold is always brilliant

Simon Buchanan, Haldons Construction
Location Plymouth
Building Use Medical Technology
Panel Core IPN Quadcore
Panel Supplier Kingspan
Panel Thickness 80mm
Panel Requirements 500m²
Services Live Environment Construction
Site Surveys
Project Management